In Hilmersdorf and Dittmannsdorf, Erzgebirgskreis (Saxony), hybrid towers for turbines of the type E-115 with a hub height of 135 meters were built for our client ENERCON GmbH.

The delivery of the required reinforced concrete segments already took place at the end of 2022. As the location is a snow-sure area, it was decided to postpone the start of assembly until spring 2023.

  • pre-assembly of concrete segments
  • pre-assembly steel sheets
  • assembly of concrete segments
  • assembly steel sheet segments

Eckdaten

Company
DTZ Montage & Sanierung GmbH
Type of performance
Plant assembly & cabeling
Tower assembly
Year
2023