The project not far from the town of Widdern in the Heilbronn district (Baden-Württemberg) is a project in the classic forest location. Having already built the foundations within the group, we were also commissioned with the tower construction. The erection of 14 precast concrete towers for the turbine type E-115 on behalf of the company Enercon was an extremely demanding project. This was reflected not least in the narrow access road and the limited space available for the pre-assembly activities. Against all odds, we were able to successfully complete the following services:

  • pre-assembly of concrete segments
  • assembly of concrete segments
  • coordination large crane work
  • installation of steel clamping wire
  • completion of built-in parts & color work

Eckdaten

Company
DTZ Montage & Sanierung GmbH
Type of performance
Tower assembly
Year
2015